item1item2item1
item1
Powerworkslogoweb
HOMEPAGEMAINIMAGEEPSN0005
|
|
|
|
|
|
item4
item5
item6
item7
item8
item14
item14a

IT Rooms

item14b

UPS Systems

item14b1

Tier 3&4 Power Solutions

item14b2

Service & Maintenance

Frimley Park Hospital Case Study

The PowerWorks with others were invited to tender to build a new computer room facility for Frimley Park Hospital. Due to an urgent requirement to expand the Accident and Emergency Department, the central computer room had to be moved to a new location within the hospital to make space for this expansion. The relocation of all the critical communications equipment was scheduled to take place over the weekend of 10th/11th November 2001 to meet operational and budgetary requirements.

The space allocated was a storeroom approximately 12.5m x 5m. The specification was to build a secure room with high levels of protection against fire, smoke and water (a boiler room in close proximity posing a particular threat of flooding). The room specification was based on the guidelines provided in the Turnbull Report on risk assessment (see Disaster Recovery Report).

The shell materials of the computer room were to meet or exceed BS476/22, maximise all available space, provide air conditioning and UPS (specification to be recommended as part of the tender document), internal fire suppression, environmental monitoring, door security, raised floor and all electrical works within the room plus full project management of build and services - with a single point of contact and responsibility.

A full site survey was carried out to assess the structural requirements plus power load of the hardware to be accommodated (allowing for expansion) in order to calculate the UPS and air conditioning requirements.

pic2 pic3

Air conditioning pipework and cables fixed to existing walls.

Floor channels laid and wall panels erected with A/C pipes and cables pulled through pre prepared duct. The duct is then sealed with intumescent material to maintain integrity of the room. Each panel is placed, locked and sealed to its adjacent panel. Panels can be cut to any size and fitted around pillars or any obstruction.Air conditioning pipework and cables fixed to existing walls.

pic4

Ceiling panels of the same construction as the walls are lifted into position, fixed to wall panels and sealed in the same way. This span (5m) required no additional support. However they can be fixed to the existing structure or new beams provided.

pic5 pic6

Ceiling panels are cut to fit round existing columns and columns are clad to maintain integrity of room. Existing lighting was left and power cut to them after construction.

Optional damp proof membrane was installed to protect from boiler room below. Optional steel sub floor completes the 6 sided box to provide EMP protection on all sides. Continuous earthing bar is fixed to base of walls and connected to floor plates.

pic11 pic12

UPS fitted with LCD control panel and maintenance bypass switch. Management software allows viewing of UPS across network and controlled unattended shutdown of servers.  

pic18 pic19

Double goods entry door with emergency push bar and external ramp to raised floor level. Base door seal drops as door closes. Single and double doors provide 1 hour fire and heat protection with smoke seals all round.

pic20 pic21

item14b2a1

Enquiry Form

HOMEicon5enquiryup

Copyright © The Powerworks Limited. Unit A, Lake Works, Portchester, Hampshire PO16 9DH

Strapanimation
Eliminate the risk
UKASWebLogo1
NICEIC1
HOMEicon1ITROOMup
HOMEicon2UPSSYSup
HOMEicon3UPSPLUSup
HOMEicon4SERVICEup

August 24th 2001
Following analysis of the tenders The PowerWorks (Computer Security) Ltd was awarded the contract."The Trust based its decision on three main criteria - value for money, compliance with the appropriate standards and tendered price.

September 4th 2001
"Planning meeting with Hospital Estates and IT Departments.Room was to be cleared and made available to The PowerWorks by the last week in September 2001. The completed computer room had to be handed over to the IT department by 2nd November 2001 to meet the deadline of relocating hardware the following weekend.The PowerWorks arrived on site.

Full Electrical Installation

Fire Suppression system with full control - linked to house alarm system - plus full environmental monitoring.

Air Conditioning System - 2 operational units  plus 1 standby unit - linked to a single control  panel.

Personnel door system with swipe card access control that monitors all entry and exit movements. Access control has manual key override.

Scheduled Completion Date Computer Room completed and handed over to IT Department

All hardware moved from existing computer room to new facility.

Client Comments "Very pleased with the decision to award the contract to The PowerWorks" "Excellent quality of build" "Good working relationship with a single point of contact for all works" "Impressed by the speed of implementation" "Would certainly invite The PowerWorks to tender for forthcoming additional computer room and recommend our service to other potential clients." All hardware moved from existing computer room to new facility.

item14b2a2

FREE Site Survey

ist26795293surveycloseup1
Home